Agencies

ERCOT

ERCOT (Electric Reliability Council of Texas) operates the electric grid that serves approximately 90% of Texas and manages the wholesale electricity market for that region.

Referenced in 94 briefingsLast referenced: May 28, 2026

Mentions

May 28, 2026

Subscribe for full access

Helios Hits 1.6 GW on CREZ Lines Built for Wind a Decade Ago

with ERCOT now tracking roughly 410 GW of large-load interconnection requests, 87% tied to data centers.

May 27, 2026

Subscribe for full access

The 445 GW Queue Gets a Gate. Capital Commitment Is the New Credential.

ERCOT's Technical Advisory Committee voted last week to advance "batch zero," a screening sequence that thins the 445 GW large-load queue through qualification, transmission study, and a financial commitment gate before final interconnection.

May 26, 2026

Subscribe for full access

Disclosure Is Coming. Developers Tracking Water Now Won't Break Stride.

Dimaag.ai has presented an 800 VDC architecture to ERCOT.

May 25, 2026

Subscribe for full access

Texas Ranks First on Power. A 5,500-Person Town Decides the Water.

No standalone Texas power or ERCOT-specific story in today's set.

May 24, 2026

Subscribe for full access

22,000 MW by 2030 Meets the First Moratorium Call

ERCOT's projection that data centers alone will need 22,000+ MW by 2030.

May 22, 2026

Subscribe for full access

Dallas Wins #1 Globally as Corpus Christi Shows the Real Constraint

Risk: ERCOT and the PUCT have no direct equivalent to Wyoming's LPCS tariff, and developers are voting with capital for jurisdictions where the regulatory pathway is pre-built.

May 20, 2026

Subscribe for full access

Water Plan Skips the 400 GW Queue. Smart Developers Won't.

Eric Goff of Goff Policy calls the queue "effectively infinite," and ERCOT's "Batch Zero" framework, plus the first PUCT-approved 765 kV lines and the ERCOT Board's $9.4 billion Eastern Backbone, are the mechanisms that convert queue position into construction schedule.

May 19, 2026

Subscribe for full access

NextEra Pays $67B for the Playbook Texas Has Run Since 2024

CEO John Ketchum's playbook explicitly requires hyperscalers to self-fund generation while utilities navigate permitting and water, the same sequencing logic ERCOT-connected developers face today.

May 18, 2026

Subscribe for full access

Opposition Hits 70%. The Siting Playbook Just Got Three Items Longer.

Texas remains the structural winner thanks to ERCOT, the PUCT, and behind-the-meter gas economics.

May 16, 2026

Subscribe for full access

Beacon Point Sets the 1-GW Template While 300 GW Wait in Queue

Risk: with ERCOT's queue exceeding 300 GW and Deloitte projecting AI datacenter demand at 123 GW by 2035, developers without an executed interconnection agreement and a credible firm-generation path won't energize on the timelines their leases assume.

May 15, 2026

Subscribe for full access

Behind-the-Meter Gas Is the New Default. Chevron Just Set the Texas Template.

Chevron's Energy Forge One subsidiary applied for a $227 million JETI tax break on a 2,500 MW gas plant near Pecos to serve a proposed Microsoft AI campus, bypassing ERCOT's 300+ GW interconnection queue entirely.

May 14, 2026

Subscribe for full access

Hill County Draws the Line. Eight Projects Now Wait a Year.

The vote lands the same week ERCOT warned the Public Utility Commission of Texas it has "concerns" with its own 368 GW load forecast for 2032.

May 13, 2026

Subscribe for full access

Closed-Loop Cooling Wins Red Oak While Somervell Calls for a Statewide Pause

The risk: Texas developers who treat ERCOT interconnection and PUCT cost-recovery rules as background noise will lose to those engaging early.

May 12, 2026

Subscribe for full access

Three Deals, One Thesis: The Capital Stack Is Buying Electrons Now

ERCOT's queue holds roughly 300 GW of pending applications.

May 11, 2026

Subscribe for full access

Recycled Water Is the Texas Permit Edge. San Antonio Just Proved It.

The mechanism is Senate Bill 6 load flexibility: facilities 75 MW and above can curtail or switch to backup generation during ERCOT peaks, unlocking idle transmission.

May 9, 2026

Subscribe for full access

Behind-the-Meter Goes Mainstream as 30% of New Datacenters Skip the Queue

The mechanics behind the shift are simple: ERCOT's queue is full, hyperscalers can't wait, and developers who own their generation own their schedule.

May 8, 2026

Subscribe for full access

IREN Stacks Power, GPUs, and Cloud Ops Before the Queue Fills

Risk: developers who submit interconnection applications before locking generation will sit in ERCOT's queue while BYOP competitors energize.

May 6, 2026

Subscribe for full access

Hut 8 Redesigned a 224 MW Hall to 352 MW. Same Footprint, Same Utility Tie.

Maura Yates of Mothership Energy, which manages over 3 GW of large load in ERCOT, says the bottleneck isn't generation or transmission.

May 4, 2026

Subscribe for full access

NERC's Rare Grid Warning Hands Texas Developers an 18-Month Window

BaRupOn's 700-acre Liberty, Texas campus will self-generate 3 GW from natural gas and recycle rainwater rather than draw ERCOT power or Liberty County aquifers.

May 3, 2026

Subscribe for full access

MARA's $1.5B Long Ridge Buy Sets the New AI Infrastructure Playbook

Behind the deal sits a structural reality: ERCOT's large-load queue swelled from roughly 63 GW at end-2024 to about 410 GW by early 2026, with 73-87% from datacenters, against an all-time Texas peak of ~85 GW.

May 2, 2026

Subscribe for full access

Federal AI Build Picks Gas in Months While Ohio's 9.2 GW Stalls

ERCOT is implementing Senate Bill 6 requirements that force large loads to install BESS, microgrid controls, and unified automation to absorb the second-by-second swings AI training imposes on the grid.

May 1, 2026

Subscribe for full access

Fort Bliss Becomes the Borderland's Third Gigawatt Build in 18 Months

ERCOT's interconnection queue hit 432 GW against 85.5 GW peak demand, and Caprock Renewables founder Raina Hornaday describes the resulting shift as "the energization of land," with distributed generation and behind-the-meter resources outpacing transmission-dependent models.

April 30, 2026

Subscribe for full access

Kiewit Books 5.4 GW for NRG as Gas Turbine Slots Vanish Through 2029

Temple's Davis is running the playbook well: separate what cities control from what ERCOT and Oncor control, quantify revenue ($7M annually rising to $12M after abatement), and refuse the zero-sum frame.

April 29, 2026

Subscribe for full access

2,600 GW Stuck in Queue. The Winners Build Their Own Power.

The Ogallala's depletion in the Permian and tightening Colorado River allocations mean Texas developers who disclose water strategy alongside ERCOT queue position will draft the rules.

April 28, 2026

Subscribe for full access

Oracle Skips the Gas Turbines: 2.45 GW of Fuel Cells at Project Jupiter

The swap drops NOx roughly 92% versus the original design and runs closed-loop cooling at negligible water draw, removing the two variables (air permitting friction, water stress) that stall large campuses outside ERCOT.

April 27, 2026

Subscribe for full access

Wisconsin Makes Hyperscalers Pay 100% of Their Own Generation Build

ERCOT's queue past 300 GW means anchor tenants without secured power by 2028 won't have premium Texas sites to choose from.

April 25, 2026

Subscribe for full access

PUCT Just Drew the Line on Which Grid Bypasses Count

The Public Utility Commission of Texas unanimously approved the first direct wind-farm-to-datacenter connection on the ERCOT grid, the same week ERCOT's high-side demand scenario, peak load above 367,000 MW by 2032, was sent back as unrealistic.

April 24, 2026

Subscribe for full access

Cancellations Quadrupled. Abilene's 2.1 GW Answer Is Off the Grid.

ERCOT has openly stated existing generation and transmission can't serve projected Texas growth.

April 23, 2026

Subscribe for full access

Capital Front-Runs the Forecast: $2B Lands Before ERCOT Hits 367 GW

ERCOT projects peak demand could triple to 367GW by 2032, with data centers driving most of that growth, and the RTO has already launched a fast-track large-load interconnection process to absorb it.

April 20, 2026

Subscribe for full access

Hyperscalers Stop Waiting on the Grid as ERCOT Stares at 218 GW

Framatome's Tony Robinson told a TCU audience ERCOT now projects 218 GW of peak demand by 2031, up from the 85.5 GW August 2023 record.

April 19, 2026

Subscribe for full access

Anchored Offtake Wins the Queue. Speculation Gets Repriced.

ERCOT's preliminary Long-Term Load Forecast projects Texas peak demand reaching 367.8 GW by 2032, more than four times the August 2023 record of 85.5 GW, with non-crypto data center load climbing from 7.4 GW in 2026 to 228.4 GW.

April 18, 2026

Subscribe for full access

Self-Supply Developers Set Their Own Clock. The Rest Wait 128 Weeks.

ERCOT filed a preliminary 2032 peak demand forecast of 367,790 megawatts with the Public Utility Commission of Texas this week, more than four times the August 2023 record of 85,508 MW.

April 17, 2026

Subscribe for full access

Behind-the-Meter Gas: 56 GW of Proof the Grid Isn't the Plan

Concord New Energy secured ERCOT approval for 1 GW of grid interconnection capacity for a Texas data center, paired with its existing utility-scale solar and battery storage assets.

April 16, 2026

Subscribe for full access

Engage Early or Inherit Someone Else's Moratorium

Developers operating where rules already exist, including Texas with its ERCOT and PUC processes, hold a structural advantage that widens with each statehouse pause.

April 15, 2026

Subscribe for full access

Build Your Own Power Plant or Lose Your Place in Line

The lesson for every developer in ERCOT territory and beyond: grid queue position is a depreciating asset if you can't defend it, and on-site generation capability is now a competitive moat.

April 14, 2026

Subscribe for full access

ERCOT's Batch Rules Are Still in Draft. Your Invoices Are Not.

ERCOT is responding with a structural overhaul: a new "batch interconnection process" that will prioritize connections, require upfront capital for grid upgrades, and reserve transmission capacity for the first time.

April 13, 2026

Subscribe for full access

ERCOT's Queue Is Separating Real Developers From the Rest

Vegas acknowledged the grid operator has never held transmission capacity for projects, and that era is ending.

April 12, 2026

Subscribe for full access

400 Projects, Two Unanswered Questions, One Legislative Clock

ERCOT CEO Pablo Vegas told legislators a transmission capacity study is underway to map available infrastructure and allocate annual interconnection capacity over a five-year horizon.

April 11, 2026

Subscribe for full access

Developers Who Testify First Write the Standards Everyone Else Follows

ERCOT's ongoing selection of large-load interconnection priorities under Senate Bill 6 adds urgency.

April 10, 2026

Subscribe for full access

Caprock Broke Ground. Projects That Can't Match It Won't.

Aligned Data Centers broke ground on Project Caprock, a 540MW, $5 billion campus near Abernathy in Hale County, while at the Capitol, lawmakers grilled ERCOT and PUC officials on who pays for the state's data center surge, and Google confirmed a 933MW natural gas plant under construction in Armstrong County.

April 9, 2026

Subscribe for full access

Nine Months to Shape the Rules Texas Is About to Write

ERCOT's interconnection queue has ballooned to 410 gigawatts of requested capacity by 2030, nearly five times the grid's all-time peak of 85.5 GW, forcing the grid operator and the Public Utility Commission to improvise new rules in real time.

April 8, 2026

Subscribe for full access

Texas Built Its Tax Break for Yesterday's Data Center Market

ERCOT's large-load queue exceeding hundreds of gigawatts of proposed demand creates the central bottleneck.

April 7, 2026

Subscribe for full access

Medina County Told Microsoft No. Here's the Playbook It Used.

Gov. Abbott's press secretary stated facilities "are required to bring their own power and to disconnect if Texans don't have what they need," and regulators require large data centers to register with ERCOT and the PUC, provide backup power, and help fund grid upgrades.

April 6, 2026

Subscribe for full access

When Military Strikes Take Down Cloud Regions, Location Becomes Strategy

Soluna closed its $53 million acquisition of the 150 MW Briscoe Wind Farm in ERCOT on April 1, buying the asset from JPM Capital Corp. and Morgan Stanley Wind LLC.

April 5, 2026

Subscribe for full access

West Texas Is Open for Business. Austin Is About to Set the Terms.

Together, these moves frame the central tension for every developer operating in ERCOT territory: Texas offers the fastest path to gigawatt-scale power, but the regulatory window for building without tighter oversight is closing.

April 4, 2026

Subscribe for full access

Developers Who Own Their Power Are Writing the New Site Selection Rules

Texas, through ERCOT's real-time load visibility and PUCT's rulemaking authority, has more institutional capacity to build a coherent framework than states stuck in reactive cycles.

April 2, 2026

Subscribe for full access

West Texas Becomes the AI Corridor While the Rest of America Waits

Gas solves the speed problem, but developers face carbon-footprint scrutiny and potential regulatory tightening.

April 1, 2026

Subscribe for full access

Utilities Waited. SoftBank, Google, and the Army Didn't.

Google's Anthropic deal puts 7.7 GW of behind-the-meter gas generation near Enterprise and Energy Transfer pipelines, bypassing ERCOT entirely.

March 31, 2026

Subscribe for full access

Texas's $25M Queue Fee Separates Serious Developers From Everyone Else

Aurora Energy Research's Liu noted federal policy often follows ERCOT precedent despite the grid's independence from FERC.

March 30, 2026

Subscribe for full access

Texas Writes the Rules While Google Writes the Check

ERCOT has estimated data center load could hit 78 gigawatts by 2031, roughly 36% of state electricity demand.

March 23, 2026

NextEra Bets $16 Billion That Texas Demand Is Real

NextEra Energy secured federal approval to build 10GW of natural gas generation across Texas and Pennsylvania, anchored by a 5.2GW, $16 billion Project Anderson in Anderson County that will feed directly into ERCOT.

March 15, 2026

Solve Water Before You Break Ground, or Else

Early reports suggest these projects still face ERCOT's severe interconnection backlog; any queue delays push Google toward supplemental gas procurement, undermining the renewable supply strategy.

March 11, 2026

Texas Developers Need No Permission. Rural Counties Are Changing That.

The resolution, sent to Governor Abbott, Lt. Gov. Patrick, the PUCT, ERCOT, and the Texas Water Development Board, follows a public hearing that drew roughly 90 residents and reflects a pattern now visible across Hood County, Somervell County, and Jack County simultaneously.

March 3, 2026

Gigawatt Ambitions, County-Level Resistance: Who Blinks First?

The GW Ranch project in West Texas takes this to its logical extreme: an 8,000-acre facility generating its own electricity from on-site gas and solar, consuming more power than all of Chicago while avoiding ERCOT interconnection queues altogether.

February 20, 2026

Big Tech's Grid Bypass Meets a 14-State Backlash

In Texas, this trend compounds ERCOT's planning challenge: if the largest loads bypass the grid entirely, transmission investment assumptions and reliability models built around centralized dispatch become unreliable.

February 13, 2026

Capital Keeps Pouring In. Communities Are Closing the Gate.

Texas isn't named in this legislative wave, but the trend is directly relevant: ERCOT's deregulated market creates different cost-shifting dynamics, and Texas's competitive posture could attract developers fleeing states with new rate guardrails, concentrating even more load on the Texas grid.

Frequently mentioned alongside